Tuesday, December 31, 2019

Living quarters/welding shop

We had to wait 5 days for the slab to cure before we could begin any work on it.
But Bob and I got to work just as soon as was possible.
In order to save money where possible, Bob took on the job of framing the building himself with friends helping out when possible.  Being a welder for over 30 years does have it's advantages.






December 31, 2019....all the overhead doors are up and we are just waiting for Jose'.  He was supposed to be here last week but he got behind on another job.  We had hoped to have tin on sides and roof before the end of this year but that's not going to happen.  Most frustrating thing about building is waiting on other people.  Happy New Year readers and hopefully by this time next year we will be out of these temp quarters and into the new house.