Sunday, April 25, 2021

The pour

On friday morning I got this text from our General Contractor.
Whoopie!  Time was set for 7am.  Pretty excited.
Then later on that afternoon I got the following text.
Like I said before, I think the General Contractor has the hardest job.  He does this ballet of sorts with all the subs, keeping a schedule that is probably just one step away from total catastrophe.  And heres just an example of what can happen in a moment's notice.
Pour is currently scheduled for Monday morning at 9:30.

Monday, April 19, 2021

Slab Talk

So I heard the trucks before I saw them and was thrilled when they turned into our place.
This is the concrete crew.  They smoothed out all the dug up places and have begun to lay plastic and rebar.  
This is just a couple of hours later and they have made a lot of progress.  What happens next is that they reinforce the wooden forms, shoot it for level, make any adjustments and then they will pour.
This is end of day, they are finished.  Pour next but no date for that.  
This is stub out for guest bathroom.  The square frame is part of the shower.
Here you can see the rebar in the trenches.
This is stub up for Master bathroom...another type of frame for another style of shower.
Pour is next and I might have a date for that tomorrow.  But this is complete until we pour. 

Thursday, April 15, 2021

Progress made

Plumber has been here since Monday working on all the stub ups, peatraps and drains.  Lots of progress has been made and hes a great guy.
If you look close at this picture you can see 4 pieces of rebar.  Those represent the drain lines for the guest bath.  We had a meeting yesterday about this bathroom.  I had just enough architecture classes in college to make me dangerous!  So even though I thought I'd drawn things to scale I hadn't and because I want a particular shower and a separate tub in here we had to draw it all out on paper several times to get it right.  And we did and I'm very happy.  But for the life of me now I cannot tell you how it all goes.  
This is mud room where washer, dryer, small utility sink, water heater, water conditioner, breaker box, spare fridge and spare freezer goes.  Seems like a lot in this room but breaker box goes recessed in the wall.  Water heater is an on demand system so it's a small unit mounted on the wall.  Water Conditioner fits under the water heater, washer, dryer and utility sink on a wall and other wall is for fridge and freezer.  
Looking from the back wall of the house past the kitchen and toward the master bedroom bath at the corner.
Drain in master shower.
Front left corner of the house where our bedroom will be, then master closet and master bath.
Right corner of house where 2 bedrooms, a guest bath, a fly tying room for Bob, the pantry and mud room will be.  
Just another shot from right front angle to back left of house.
Plumber thinks he will finish up today provided he gets the specs for the water conditioner.  Hopefully sometime this morning.  After he does that then he can smooth top, and put on plastic.  After that the concrete guys come and place and tie rebar and then pour.  No date on that yet we have to wait until plumber is finished.

Wednesday, April 7, 2021

Good help is so hard to find!

Today is Wednesday, plumber was supposed to be here on Monday but got held up by another job.  No biggie...it happens.  And then Tuesday but was held up again but I did meet with the electrician who has to run a line to the island in the kitchen for plugs and the freezer/ refrigerator drawers.  And to mark where breaker box will be in the mud room.  
Electrician was back this morning to do his thing and plumbers helper did not show up so tomorrow.....is what I'm being told.  I think after that is plastic, re-bar and pour but dont quote me...
This is for island in the kitchen.
This is stub up for breaker box in the mud room.  

Trenches, trenches and more trenches.

As you can see we have a couple more trenches.

This is for the plumbing...grey and black water lines.  Grey water is water from showers, sinks and washing machine.  Black water is from toilets usually combined with one sink line to help everything go into the septic tank.
While we wait for the plumber to return we (Bob and I got busy with the last of the water line from temp quarters to new house and electric from meter to down to where new house will be built.  
The black and white wires are the power.  The smaller green wire is the ground wire.  
All three wires are taped together along with the end of the muletape that was already pulled through and I'll stay up here and make sure that when Bob starts pulling at the other end the spools don't over roll.  It went really smoothly.  But we are not done yet, we need to pull from this end over to where the wire will hook into the existing power.  We wont do the actual hooking up...that's for the electrician but we need to get it over there.
So if you look closely and enlarge the picture just a bit you can see just to the right of the Bobcat where this wire needs to go.  And if you look down at the bottom of this picture you can see the pipe on the right...that's what this wire needs to go in in order to reach that spot on the other side.  
So this little black piece of foam is called a " mouse".  Tied onto it is a piece of string.  We will use a vacuum cleaner on blow to blow the mouse with the string through to the power grid.  Then onto to string we will tie the muletape and taped on the muletape will be the wires....got that!  
TaDa!  Just like that...took about 10 seconds.  
And there's the wire.  
And this is muletape.  It's a flat nylon rope.  Bob used it in the phone company and we bought a couple spools of it when we found it on line.  The stuff is great.  We always have some in every vehicle that we own as well as the Kawasaki Mule and of course it's in the shop and well house.  You never know when you are gonna need it and it lasts forever...well maybe not forever but certainly a long time.  

Saturday, April 3, 2021

Here we go!

The crew came out and placed these stakes for the corners.
So they dig the parameter first and the shoot a string line to find what is level.  We thought this area was fairly level but theres about 2 feet difference from one side to the other.
So heres what it looks like before they start framing it out.

And here it is framed.  You can see on the left side there are more boards than on the right side.  Looks caddiewompus but that absolutely level from side to side, front to back.  
There is a trench that spans the length of the house and there are 2 trenches that intersect this trench.  The trenches have several jobs.  This is where some plumbing will run in conduit and also electric lines in conduit also.  The electric in this particular home is not much because I only have one line that needs to go in the middle of the floor.  It's actually for some plugs in my island in the kitchen.  It's also for a dedicated plug for my freezer drawers that are also in the island.  The rest of the electric will be strung through the walls.  
That's it for today.  I met with the plumber this morning to go over the rough in.  Hes supposed to be back on friday to start the rough in.  Then I think maybe the electrician comes to do his small part just for this stage.  Then comes I believe the plastic and rebar.  

Sunday, March 21, 2021

Getting into position

That big Live Oak right there will be at the back right of the patio.  If you look real close you can see a bit of orange...that's the back corner right of the house.  The front door would be just to my left and looking out toward the opposite way.
Fill has arrived.  This is ( for those who dont know how a home is built) for the slab.  This helps level up the ground and build up areas that are low.  It's also where your plumbing sits...most people think plumbing is in the slab...its not, its actually in this fill in trenches.  It leaves space for stuff like pea traps etc.  Gotta have those if you want your water to drain.  
Surprise,  surprise, surprise.  Tin for house has arrived...early.  was supposed to be here on Monday but it came today.  Lots to do before it can be put on but its here.  
I had hoped to post pictures of the fill being spread and the forming up for the slab.  But as with all things eagerly anticipated we have been delayed.  Not sure of exactly why other than the crew did not finish up with the job preceding ours so hopefully tomorrow which is Monday March 22.  
The picture above shows the corner of the shop.  In the middle of the picture is part of a bucket that we buried to show us where we made a junction for the electric wire and the water line for the house.
this is the trench that will carry the electric line, water and possibly coaxial cable for the internet.  Our antenna is here at the shop and we dont want to move it because if we should ever have long term guests then they can stay in temp quarters and have TV and internet.
I think if you blow up this last picture you can see the end of the trench and just beyond that will be the house.
This white pipe will carry our water from the well to the house.  The larger pipe will serve as a protective covering for the electric line and coaxial cable.  You cannot direct bury that kind of stuff in the ground as it can erode and then youd have to dig the whole line up to find out where your trouble spots are.  Probably against some code somewhere as well.  
This is the electric line that goes from the meter all the way down to the house.  
Here it is all spaced out and ready to have a piece of mule tape threaded through before we glue it up and then pull the wire.
All glued up and in the trench for now.  Cows walk through here and we dont want them stepping on the pipe.  All caught up now on progress till we get guys in to spread fill and start framing.  Fingers crossed it's this week.  Although now weather report says tomorrow is 50% chance of rain....